top of page
20231108_131230118_iOS.jpg

Dumbryden - Edinburgh

Location: Westerhailes, Edinburgh

Value: £2.2 million

Project Duration: 24 Weeks

Contract: SBCC Design & Build contract, 2016 Edition

Client Team: City of Edinburgh Council

IRS were appointed to this contract for the fabric upgrade to 140 City of Edinburgh council / Private Properties, this is part of the  City of Edinburgh councils 3 year mixed tenure improvement service (MTIS) pilot.

Fabric upgrades comprised of the following:

  • Pre / post Energy performance assessments

  • Installation of 130mm Mineral wool class ‘A1’ External Wall Insulation.

  • Installation of new Brise Soliel feature coloured cladding panels to drying screen areas.

  • Engineered Installation of Roofline extensions with upgraded ventilation and critical cold bridge detailing.

  • Removal of old and installation of Marley roof system including new rafter extensions.

  • Installation of new Window system

  • Upgraded Mechanical Ventilation strategy.

  • Installation of New secure entry fire Doors.

  • Upgraded top up loft insulation.

  • Installation of new underfloor insulation.

  • Upgraded fire coating decoration works.

  • Upgrade and reroute of rainwater disposal systems.

Due to the success of this project, it will now be rolled out across the city of Edinburgh to help accelerate energy efficiency fabric maintenance and repairs in mixed tenure blocks. As part of our commitment to Social Value, IRS had the opportunity to refurbish two local playgrounds through this contract which will benefit the community for many years to come.

Similar Projects

Logie manor phase 3 image 8.jpg
Manchester Project (46).JPG
MAGDELANE_2.jpg
bottom of page