Cooper House, Hulme, Manchester: balconies on the nine-storey block
COOPER HOUSE · ACROSS THIS PROJECT
STAGE
PCSA to Gateway 2
STOREYS
Nine
HOMES
91 apartments
VALUE
£2m
OCCUPIED
Yes
PROJECTS / NORTHERN REGION / COOPER HOUSE

Cooper House

A nine-storey occupied Higher Risk Building of 91 apartments in Hulme, Manchester. IRS is working under a PCSA to take the replacement of its combustible cladding through the Building Safety Regulator’s Gateway process.

KEY FACTS
Contract value
£2 million
Client
The Guinness Partnership, agent AtkinsRéalis
Our role
Principal Contractor, under a PCSA
Contract
JCT Intermediate Building Contract 2024 (ICD)
Regulatory stage
Higher Risk Building, PCSA through to Gateway 2
Location
Booth Street West, Hulme, Manchester
Size
91 apartments over nine storeys
Built
1970s
Nation
England
Occupied
Yes, throughout

What the job involved

Cooper House is a nine-storey Higher Risk Building of 91 apartments in Hulme, Manchester, originally built in the 1970s. The project replaces the combustible façade cladding to the entrances, balconies and soffits, delivered through the Building Safety Regulator’s Gateway process while residents remain in their homes.

Appointed as Principal Contractor, IRS will remove the existing Trespa cladding system and install a new Rockpanel cladding system, with PermaRock render to the soffits, covering the external columns, balcony dividing walls, access walkway soffits and the entrance lobby. The insulated PVCu and PPC spandrel panels to the windows and curtain walling will be replaced, alongside new fire-stopping and remediation of the PPC window flashing to the west and east façades. Services within the access walkways and balconies will be relocated to suit the new build-up.

IRS has entered into a Pre-Construction Services Agreement to carry out the building control application through the Building Safety Regulator’s Gateway process. Section 1 covers completion of the Contractor’s Design Portion and Gateway 2 approval; Section 2, subject to Section 1, delivers the works. Design, surveys, procurement and cost planning are being coordinated to secure a de-risked scheme and a fixed contract sum.

RESIDENT LIAISON

A dedicated Resident Liaison Officer coordinates with residents to manage expectations, give updates and resolve issues as they arise. With neighbouring homes and educational buildings close by, engagement extends to managing traffic and logistics around the building, and every household receives a Welcome Pack covering the scope, emergency procedures and fire strategy.

The programme

STAGE 01
PCSA appointment

IRS entered a Pre-Construction Services Agreement to take the building control application through the Gateway process.

STAGE 02
Design to Gateway 2

Section 1 covers completing the Contractor’s Design Portion and gaining Gateway 2 approval from the Building Safety Regulator.

STAGE 03
Scheme de-risked

Design, surveys, procurement and cost planning coordinated towards a de-risked scheme and a fixed contract sum.

STAGE 04
The works

Section 2, subject to Section 1, delivers the works, with residents in their homes throughout.