Advent 2 and 3, Manchester: white and brown clad apartment blocks with balconies, seen from below
ADVENT 2 AND 3 · ACROSS THIS PROJECT
VALUE
£9.7m
PROPERTIES
242
DURATION
44 weeks
FIRE DOORS
80+
FUNDING
Building Safety Fund
PROJECTS / NORTHERN REGION / ADVENT 2 AND 3

Advent 2 and 3

242 properties in Ancoats, Manchester, where non-compliant external cladding in render, copper and timber was designed out and replaced with a non-combustible External Wall Insulation and façade system, alongside compliant balcony decking and more than 80 new fire doors.

KEY FACTS
Contract value
£9.7m
Client
Urban Bubble, Thomasons, DFC
Contract
JCT Standard Building Contract 2016 with Contractor’s Design Portion
Location
Ancoats, Manchester
Region
Northern Region
Size
242 properties
Duration
44 weeks
Funding
Building Safety Fund

What the job involved

IRS was appointed to design and replace all non-compliant external cladding, which incorporated several different finishes including render, copper and timber. The contract also covered compliant rhino decking to balcony and walkway areas and the installation of over 80 new fire doors.

We were tasked with designing and installing a new non-combustible External Wall Insulation and façade system with compliant fire stopping. Holding that design role alongside our architectural and engineering partners let us explore alternative materials that performed as well or better, cost less, and kept a similar aesthetic finish so the client could satisfy planning.

An offsite storage and recycling strategy minimised disruption: non-combustible materials left site as soon as they came off the façade, and company pickups ferried materials and waste to cut commercial traffic. On social value, IRS worked with the City Zen charity in Greater Manchester, supporting the employment of ex-offenders and servicemen. Across the Advent projects, 95.62% of project waste was diverted from landfill.

How we evidence social value →

WHAT RESIDENTS SAID

“Just wanted to say a big thank you for responding to the issue with the builders. So often, things like this get swept under the rug and forgotten about. It really meant a lot that I was listened to.”

LAURAN · RESIDENT

WHAT THE CLIENT SAID

Their attention to resident liaison and communication was exemplary, and so much so they have been chosen to remediate another BSF project in Manchester where I am Director.

ROBERT MACKAY · DIRECTOR · ADVENT 2/3